Grid connection for all phases include site survey,HT and Lv line construction installation and commision of substation
Project Description
Challenges
- Material handling was big show stopper to all project phase
- Way leave compensation was challenge to all project phases as it delays the project s and lead to extra cost
- Phase one was done during summer period rain was big challenge as most of the sites where in remote area in gravel roads which was hinder our plan to close the project on time
CONSTRUCTION PROJECTS
PROJECT DETAILS
Categories: | |
Client: | Helios Towers Tanzania (HTT) |
Location: | South zone in Tanzania |
Completed: | PHASE ONE WAS COMPLETED ON 13TH JUNE , 2017 PHASE 2- WAS COMPLETED ON 7TH AUGUST, 2017, PHASE 3- WAS COMPLETED ON 24TH DECEMBER, 2017 |
Value: | PHASE 1-396,404,000. PHASE 2-201,205,000. PHASE 3-805,427,195. |
Architect: | Hematec |
CONTACT
Shekilango Road,Behind Sinza palestina Hospital .
+255 222 461 895
info@hematec.co.tz
P.o.Box 34078 Dar es Salaam, Tanzania
+255 222 773 389
Mon - Sat: 9:00 - 18:00